Modular Cleanroom Assemblies for Ballroom Applications

Cleanroom Modular/Take Off-Site Solution

Confidential Client – France & Singapore

Off Site Sub-Assemblies

• Design - Standardised, Repeatable, Agile & Flexible – Future proofing and repurposing • Reduction in Design Costs • Cost estimates reliability • Reduced Technical risks of the product approval process • Cycle time reduction – faster start up of facilities • Clean manufacturing environment – Closed Process

Our Approach • Standardised design of Ceiling Modules & Partition Skids • FAT, Factory assembled modules • Modules based on • Flat pack ceiling modules c/w integrated services • Skid mounted partitions c/w Utility plates, Safe change & ducting

• Standardised CR-RCU (1.6m3/s) • Manufacturing / subassembly • Construction Sequencing • Delivery Capability • Procurement Strategies

Pre-Assembled Ceiling Modules

Pre-Assembled Ceiling Modules

• Module size 5m x 2.1m • Aluminium honeycomb 60mm thick panels • Preinstalled Lights and small services • Openings formed for Terminal HEPA housings • Pre-assembled Ceiling Mounted Utility Panel • Uni directional Grid for Cable Management

Preinstalled Services

• Lights and small electrical services installed with flying lead and plugs • Cables brought to ceiling grid • Plug & Play cable looms supplied to connect services

Pre-Assembled Partition Skid Modules

• 200mm infill Service Mullion positioned between each partition skid

200

Partition Skid Assembly

Factory Assembled modules

• Stainless Steel Skid Assemblies • Complete with Safe Change Unit • Ducting • Stainless Steel Utility Plates

HVAC Airflow Concept

• Standard CR-RCU Concept • Repeated Design • Integrated Controls on all HVAC Equipment

HVAC Equipment

• Offsite FAT for all HVAC Equipment • Technically Compliant solutions • Key Vendors

• JCI – CR-RCU • Trox CAV/VAV • Camfil – Safe Change & Terminal Housings

CR-RCU’s

Key Features: • Integrated factory tested Control System Fan options to achieved A+ Rating (Interchangeable for future) • Integrated CAV & VAV’s • Standard Frame Size • Common Components to all units • Full Fresh and Re-Circ Versions • Minimal on site install and commissioning

Ductwork Assembly

Push Fit Ductwork Connections • Fittings and ducts are manufactured from zinc coated sheet metal • Other material than galvanised can also be supplied, for example • Stainless steel • Aluminium • Plastic Coated Products • Aluzink Corrosive category Sheet metal material

C3 C4

Galvanized steel sheet metal Z 275

Aluminium sheet metal Plastic HB-polyester coated galvanised steel sheet metal Plastic epoxi+PE-painted galvanized steel sheet metal Aluzink sheet metal AZ 185

C5

Stainless steel sheet metal

Module Assembly - Electrical

• All electrical containment integrated with docking station • Home run cable to go from individual modules to dedicated distribution board with plug and play connections • Pre Tested cabling to reduce on site commissioning and testing time • Complete flexibility for alterations with

Tempered CHW

CHW skid & distribution • Package unit is mounted on a fabricated stainless steel support base with interconnecting pipework • Power supply is typically 400V, 3 phase, 50Hz, 10 Amp • Skid fully 3D modelled available for BIM requirements. • Fully assembled and tested off site (FAT) and ready to install • Integrated dosing pot, expansion vessel, fill sets, heat meters, duty/standby pumps • Control panel, featuring touch screen with access to all system parameters and energy data. Remote access and retransmission possible • Piped distribution loop connects to CR-RCU’s, providing sensible cooling for the dry coil concept. Controlled locally at CR-RCU

Construction Sequencing

• Link below to Construction Sequencing & Assembly Video

https://youtu.be/4SlmjGxEsLM

Delivery Strategy -

• Integra is a single source work package in which we take responsibility for design and construction of the project and manage the safety, cost, schedule and quality of the works and ultimately the performance of the cleanroom under one contract.

• We take ownership of the solution and guarantee the following performance criteria;

• Particulate

• Humidity • Containment • Illumination

concentration • Room pressurisation • Temperature

• Our experienced cleanroom designers and engineers work with the customer from initial concept through to detailed design, dealing with any unique site factors and complexities and provide robust solutions that meet both local codes and regulatory requirements.

Procurement Strategy

How will the customer procure the project?

• Fast track project • Single source Integrated Cleanroom - Design heavy & front end loaded • Design localisation of standard designs & vendors to

comply with local regulations • Early engagement preferable • Early commitment from customer

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 12 Page 13 Page 14 Page 15 Page 16 Page 17 Page 18