Comp #: 606 Slate Floor - Replace

Quantity: Approx 1,550 GSF

Location: Common areas Funded?: Yes. History: 2014

Comments: This flooring should enjoy a full useful life. Maintain as needed as an operating expense. Funding for eventual replacement on roughly the schedule below. Continue to monitor and adjust as needed in future Reserve Study updates.

Useful Life: 30 years

Remaining Life: 22 years

Best Case: $ 25,000

Worst Case: $ 37,000

Cost Source: Allowance Estimate

Comp #: 609 Tile Floor - Replace (West Room)

Quantity: Approx 1,180 GSF

Location: West room flooring Funded?: Yes. History: 2014

Comments: As part of ongoing maintenance program, inspect regularly and repair or replace damaged sections as needed. With ordinary care and maintenance, tile in interior locations can last for an extended period of time, but replacement is often warranted eventually to enhance and restore aesthetic appeal in the common areas. Replacement costs can vary greatly depending on size and type of tiles selected. Our recommendation is to replace at the approximate schedule shown here, but this schedule can be adjusted at the Association's discretion.

Useful Life: 30 years

Remaining Life: 22 years

Best Case: $ 20,000

Worst Case: $ 27,200

Cost Source: Allowance Estimate

Association Reserves, #6510-0