3 Final 2022-23 ReserveStudy-07-29-2022 reduced-compressed

Golf

Comp #: 411 Drinking Fountains - Replace Location: Throughout course Funded?: Yes. History: 2022: $36,000 Comments: Plan to replace on the schedule below.

Quantity: (8) Fountains

Useful Life: 10 years

Remaining Life: 9 years

Best Case: $ 32,000

Worst Case: $ 40,000

Cost Source: Client Cost History

Comp #: 916 Starter Building - Refurbish Location: Adjacent to El Saguaro Clubhouse Funded?: Yes. History: Unknown

Quantity: (1) Total

Comments: This component represents an allowance for maintaining the starter building. Building should be inspected, cleaned and small maintenance projects made as an Operating expense. Typical Reserve-funded projects may include: exterior painting, roof repairs/replacement, awning replacement, new windows and doors, lighting, signage, air conditioning, electrical repairs, etc. For smaller buildings, any single project may not individually meet the threshold for Reserve funding, but combinations of projects done together may become significant. Any common area building has significant aesthetic value in terms of curb appeal and first impressions and should be maintained to a high standard.

Useful Life: 15 years

Remaining Life: 5 years

Best Case: $ 5,000

Worst Case: $ 10,000

Cost Source: Allowance Estimate

Association Reserves, #6510-0