Stage 1 Stage 2 Stage 3 Stage 4 Stage 5
Stage 3 – Project Mobilisation Statutory Approvals Some building works have statutory approval processes to be sought before any works commence. It is the responsibility of the Surveyor to ensure all approvals are in place before works commence. These could include • Planning Permission • Party Wall matters (contact our Estates Team for guidance) The Surveyor may liaise with the supplier or an external consultant to ensure these approvals have been obtained before any works commence. The preferred approach for any given project can be agreed with the Senior Surveyor Where planning is required consideration should be given to making as early a start as possible once the project is confirmed to avoid delays with delivery. • Conservation Area Consent • Building Regulations Approval