“Building a good foundation for any project is essential. And that is, quite literally, our business as we lay the groundwork on some of the Midwest’s most vital infrastructure projects. To meet the growing needs of new and existing clients, we’ve expanded our capabilities to include alternative and renewable energy projects.”

-Jason Smith, General Manager | Site Group

FEATURED PROJECTS

Contract Value: $13,375,803 Nestlewood Solar Farm

Our expertise in grading, clearing, electrical trenching, and the creation of access roads laid the foundation for future development at this vast 422-acre infrastructure project. Our team ensured that the area was primed for the next stages of construction. We also successfully drilled 75 foundations for the switch-yard and substation, providing critical support for the region’s power infrastructure.

We played a crucial subcontracted role in developer NRP Group’s transformational The Collins at the Riverbend project by developing the site on Cleveland’s Scranton Peninsula. Our team handled clearing, site demolition, erosion control, grading, excavation, underground utilities, and constructing retaining walls. We also provided pedestrian right-of-way grading for staircases and sidewalks—a key feature in revitalizing pedestrian access & usability for the area along the river.

CLIENT

CONTRACT

ARCHITECT

Contract Value: $3,370,878 Cambria Substation

NRP Group

$4,896,679

Boarman Kroos Vogel Group

Our team executed a comprehensive site development plan, installing SWPPP items for environmental protection, removing an asphalt road, stockpiling topsoil, and completing grading and spoil removal. We installed storm pipes, catch basins, outlet structures, and a retaining wall, graded roads, excavated a basin, lined the embankment, and placed riprap, ensuring the site is ready for future development.

Nonsed minventi debiti ute es dolor simintur?

SLATED FOR 2025

Location: Bowling Green, OH Contract Value: $3,900,000

Bowling Green Data Center

600 acre site with 3-acre substation that includes excavation, site prep and drilling concrete caissons.