Cases Part 4 2023 Final

Adjudication Case Law Update 2023: Part 4

Set off against adjudicator ’ s decision

FK Construction Limited v ISG Retail Ltd

[2023] EWHC 1042 (TCC) Justice Joanna

Smith DBE judgment 5 May 2023

In the fourth edition of our 2023 Court Decision Summaries, Kenneth Salmon MCIArb, consultant solicitor at Slater Heelis LLP, summarises four court decisions relating to the enforcement of adjudicators' Awards under the Housing Grants, Construction and Regeneration Act 1996.

Repayment following final

determination

ISG Retail Limited v FK Construction

Limited [2023] EWHC 2012 (TCC) Adrian

Williamson KC judgment 2 August 2023

Legislation The “ Act ” means the Housing Grants, Construction

and Regeneration Act 1996, as amended by the

Local Democracy, Economic Development and Construction Act 2009 Pt 8. The ‘new’ provisions

In Part 4

apply to contracts entered into on or after 1 October

Jurisdiction – Commencement of true

2011. The Act applies to England and Wales,

Scotland and Northern Ireland.

value adjudication before payment of

notified sum

The main regulations are contained in the Scheme

Henry Construction Projects Limited v Alu-

for Construction Contracts (England & Wales) Regulations 1998 (the ‘Principal Regulations’). 1

Fix (UK) Limited [2023] EWHC 2010

(TCC) District Judge Baldwin judgment 23

They have been amended by the Scheme for

May 2023

Construction Contracts (England & Wales) (Amendment) (England) Regulations 2011 2 (the ‘new Regulations’). The new Regulations apply

Natural Justice – Amount of material

only to contracts for construction operations in

and lack of time

England entered into on or after 1 October 2011. For

Home Group Limited v MPS Housing

earlier contracts, the Principal Regulations apply.

Limited [2023] EWHC 1946 (TCC) Mr

Northern Ireland has its own scheme: the Scheme for

Justice Constable judgment 25 July 2023

Construction Contracts in Northern Ireland 1999 as

2 Scheme for Construction Contracts (England & Wales)

1 Scheme for Construction Contracts (England & Wales)

(Amendment) (England) Regulations 2011 (SI

Regulations 1998 (SI 1998/649).

2011/2333).

1

1998 4 applies. There are new separate regulations

amended by the Scheme for Construction Contracts

in Northern Ireland (Amendment) Regulations

for Wales, applicable to contracts for construction

(Northern Ireland) 2012. The Northern Ireland

operations in Wales entered into on or after 1 October 2011. 5

Scheme is broadly similar to that in force in England

and Wales.

A reference to “the Scheme” is to the Principal Regulations for England and Wales, or the Scheme

There are separate regulations for contracts for work

in Scotland applicable to contracts made on or after 1 November 2011. 3 The new Regulations apply only

for Scotland, Wales, or Northern Ireland, as the

context requires.

to contracts for work in Scotland entered into on or

after this date. For earlier contracts the Scheme for

Construction Contracts (Scotland) Regulations

Summary

Jurisdiction – Commencement of true value adjudication before payment of notified

sum

Henry Construction Projects Limited v Alu-Fix (UK) Limited [2023] EWHC 2010 (TCC)

District Judge Baldwin judgment 23 May 2023

The obligation to make immediate payment arises when there is a notified sum under s111 of

the Act, not when an adjudicator later awards payment. A true value adjudication may not be

commenced or continued and the adjudicator will not have jurisdiction to determine a true

value adjudication until payment of a notified sum has been made. Where there is a genuine

dispute as to whether or not a notified sum exists, a true value adjudication may be allowed

pending a decision as to that issue.

Natural Justice – Amount of material and lack of time

Home Group Limited v MPS Housing Limited [2023] EWHC 1946 (TCC) Mr Justice Constable

judgment 25 July 2023

3 Scheme for Construction Contracts (Scotland)

5 Scheme for Construction Contracts (England and

Amendment Regulations 2011 (SI 2011/371).

Wales) Regulations 1998 (Amendment) (Wales)

Regulations 2011 (SI 2011/1715) (W.194).

4 Scheme for Construction Contracts (Scotland)

Regulations 1998 (SI 1998/687) (S.34).

2

Complexity and/or volume of material and consequent constraint of time in which to respond

were inherent in the process and of themselves no bar to enforcement. Cases involving

significant amounts of data entitled the adjudicator to proceed by way of spot checks and/or

sampling in such manner as s/he should determinate.

Set off against adjudicator ’ s decision

FK Construction Limited v ISG Retail Ltd [2023] EWHC 1042 (TCC) Justice Joanna Smith

DBE judgment 5 May 2023

A court would have discretion to permit the set off of one adjudicator’s decision against another, as an exception to the pay now argue later principle where:

a) There was a statutory right of set off which did not offend the Act.

b) The set off was a consequence of the decision itself.

c) In its discretion where there were two (or more) valid and enforceable decisions between the

same parties, and proceedings to enforce each decision, the effect of which was that money was

due to each party.

In this case the principles were not satisfied and the decision was enforced in full without set off.

Repayment following final determination

ISG Retail Limited v FK Construction Limited [2023] EWHC 2012 (TCC) Adrian Williamson

KC judgment 2 August 2023

Following the case of Aspect and Higgins. This is the sequel to the earlier case in which repayment was

now ordered.

3

Court decision summaries in full Click on the options below to read a full summary and analysis.

Jurisdiction – Commencement of true value adjudication before payment of notified

sum

Henry Construction Projects Limited v Alu-Fix (UK) Limited [2023] EWHC 2010

(TCC) District Judge Baldwin judgment 23 May 2023

Henry applied for summary judgment to enforce the "true value" adjudication decision of Mr

M.T. Molloy dated 6 March 2023 ("TVA") awarding them £191,753.88 plus interest. Alu-Fix

resisted on the basis that Mr Molloy lacked jurisdiction because the TVA had been commenced

prior to Henry having paid them the notified sum due to them under the JCT Contract between

the parties.

Alu-Fix had made a payment application. Henry failed to make payment or to issue a payment notice or (as it was later found) serve an effective pay less notice ( “ PLN ” ). Alu-Fix commenced a smash and grab adjudication before Mr Rayner (“SGA”). At that point, without making payment of the application, Henry commenced the TVA. Alu-Fix asked Mr Molloy to resign

because Henry had commenced the TVA before making payment of the notified sum. Mr

Molloy found he had jurisdiction because at that time Mr Rayner had not yet made any decision

and it remained to be seen whether the sum claimed in the SGA (and disputed by Henry) was

or was not due. Mr Molloy stayed the TVA pending the outcome and payment of any sum

found due by Mr Rayner.

4

Mr Rayner decided there was no PLN and found Henry liable to pay the sum claimed. They

made payment to Alu-Fix, whereupon Mr Molloy proceeded with the TVA, finding in favour

of Henry.

The issue before the court was one on which there was no direct authority: could a paying party

commence a TVA where the question of its liability to make the payment claimed due was

genuinely disputed and had yet to be determined in an existing SGA?

The court referred to the decisions of • O'Farrell J in the recent case of Bexheat v Essex Services Group 6 , • Jackson LJ in Grove Developments Ltd v S&T (UK) Ltd 7 , and • Stuart-Smith J (as he then was) in M Davenport Builders Ltd v Greer 8

from which it derived the following principles:

- Where a valid payment application was made, and no payment application or PLN was

given, the payer was obliged to pay the notified sum by the final date for payment (s111

of the Act).

- If payment was not made, the payee was entitled to seek an adjudication award in its

favour.

- Where a party was required to pay the notified sum by reason of its failure to serve a

payment notice or PLN, it was entitled to embark upon a 'true value' adjudication in

respect of that sum but only after it had complied with its immediate payment obligation

under s111 of the Act.

- It was clear that the payer became free to commence a true value adjudication when

(and only when) he had paid the sum ordered to be paid by the earlier adjudication.

Henry’s case Henry argued that this case differed from those previously decided, in that at the time of

commencement of the TVA there was an ongoing "genuine dispute" as to the validity of the

PLN. Thus, unless and until there was an adjudication decision that there was no valid PLN,

no "immediate payment obligation" arose or subsisted. The embargo upon launching a TVA

6 [2022] EWHC 936 (TCC).

7 [2018] EWCA Civ 2448, (2018) 181 ConLR 66, [2019] Bus LR 1847 . 8 [2019]EWHC 318 (TCC), [2019] Bus LR 1273, [2019] BLR 241.

5

prior to the payment of any immediate payment obligation was not engaged and no question of

jurisdiction could arise. The payment obligation only became immediate upon Mr Rayner

finding the PLN invalid and was discharged within the timeframe set down by him. They also

drew the Court's attention to Stuart Smith J's analysis of Harding (t/a MJ Harding Contractors)

v Paice in the case of Davenport in which it was said the Court of Appeal implied that it was

not an essential prerequisite to relying upon a later true value adjudication decision that the

earlier immediate obligation should be discharged before launching the later true value

adjudication. Paice did not pay its immediate obligation under the third adjudication before

launching the fourth, and they were not precluded from proceeding with or relying upon the

fourth adjudication for that reason. This suggested that the critical time would be when the

court was deciding whether to enforce the immediate obligation.

Alu-Fix submitted that the authorities were clear: you could not commence a TVA until the

existing liability had been discharged.

What is the date of the immediate payment obligation in this case?

The court held that the resolution of the issue lay in determining the commencement date of

the immediate payment obligation: was it the final date for payment under s111 of the Act? Or

in the case of a genuine dispute as to entitlement, the date of the decision of the adjudicator?

Section 111(1) of the Act provided that the notified sum must be paid by the final date for

payment. This created the immediate payment obligation ( Bexheat para. 76(ii)). And that is

what Mr Rayner decided in the SGA.

The existence of a genuine dispute as to the existence of an immediate payment obligation did

not alter the position. For it to be allowed to do so would be to undermine the right to payment

and to tip the balance in favour of the disputing party. And it might also require the court to

decide whether a dispute was genuine or not. The payer could protect itself by serving a PLN.

In what circumstances might a genuine dispute as to the existence of a PLN entitle the

payer to commence a TVA before payment?

Recognising there could be a tension between an apparently premature TVA being a nullity or

surviving for the purposes of reliance, the court suggested the following solution. If an adjudicator in Mr Rayner’s position upheld a "zero" PLN, or the validity of a payment application was successfully challenged, there would have been no ‘notified sum’ within the

6

meaning of the Act and therefore no immediate payment obligation. As such a TVA may well

not, on the facts, be found to be premature and reliance upon it might well be permitted.

In dismissing the summary judgment application the learned Judge concluded thus:

“Overall, in my view, the outcome in this case, whilst not closing the door on commencing a

TVA prior to the outcome of an SGA and later relying upon the outcome, ought to discourage

such a course in areas of spurious SGA dispute, but not deter those who have a sufficient level

of confidence that any dispute raised should result in a finding of no immediate payment obligation having b een established.”

Comment

As before (see Paice), the door is not completely closed on commencing a TVA whilst a SGA

is anticipated or in progress and before making payment. The question of jurisdiction in the

TVA may yet turn upon the outcome of the SGA. If it is later established that the payment

application in question is invalid, or an effective payment or pay less notice has been given,

there will have been no notified sum due and payable under s111 of the Act and therefore

nothing to prevent the TVA from having been properly commenced and continued. The

circumstances in which such a course proves worthwhile, may be limited. If the SGA decides

no notified sum, there will be no payment obligation and no need for a TVA. On the other hand,

if those questions arise and can be dealt with on enforcement (under part 7 or part 8), then the

TVA may well have utility.

Natural Justice – Amount of material and lack of time

Home Group Limited v MPS Housing Limited [2023] EWHC 1946 (TCC) Mr Justice

Constable judgment 25 July 2023

Home Group applied to enforce the decision of Mr Derek Pye awarding them some £6.5m in

what was the second of two adjudications between the parties. In the first adjudication it was

held that MPS had wrongfully determined a contract under which they had engaged Home

Group to perform property maintenance and repair work. The second adjudication concerned

assessment of the termination losses. MPS opposed enforcement on the grounds of breach of

the rules of natural justice, submitting that:

(i)

the sheer volume of material comprising the referral, coupled with

7

(ii) Home Group’ s unreasonable refusal to provide MPS with data or access to the underlying documents until the last moment, and

(iii) a lack of sufficient time for MPS and its experts to interrogate and fairly respond to

the referral.

Volume of materials

MPS said that if the electronic data comprising and supporting the referral was reduced to paper

it filled 127 double-sided lever arch files, equivalent to 32 standard boxes. Home Group pointed

out that the hard copy documents delivered to the adjudicator filled 7 boxes. The court held

that irrespective of whether the correct number was 7 boxes or 32 boxes, the quantity of

information of itself did not present a valid basis for challenging enforcement.

Access to data Home Group’s offer of access to its data before the adjudication was conditional upon

agreement to a sampling exercise. The court said that had MPS reserved its position as to the

nature and extent of sampling but requested access it would have been difficult for Home Group

to have refused. Or had it refused, the complaint would then have had substance.

Time to respond

MPS and its experts would have had sufficient time to respond if they had acted immediately

instead of complaining at the lack of time and losing three weeks in tactical manoeuvring. The

court noted that the adjudicator was able to address the issues (including particularly the

allegations of quantum duplication) by undertaking a sampling exercise and that MPS did in

fact make considerable inroads into the quantum of the claim which was originally in excess

of £8m.

In reviewing the considerable body of case law on the subject, the court concluded:

(1) Adjudication decisions must be enforced even if they contained errors of procedure, fact or

law.

(2) A decision would not be enforced if it was reached in breach of natural justice and the

breach was material, i.e. led to a material difference in the outcome.

(3) Complexity and constraint of time to respond were inherent in the process and no bar in

themselves to enforcement.

8

(4) In cases involving significant amounts of data, an adjudicator was entitled to proceed by

way of spot checks and/or sampling. How this should be carried out was a matter of substantive

determination by the adjudicator and an error in approach, in the absence of some particular

and material related transgression of natural justice, would not give rise to a valid challenge.

The decision was enforced.

Set off against adjudicator ’ s decision

FK Construction Limited v ISG Retail Ltd [2023] EWHC 1042 (TCC) Justice Joanna

Smith DBE judgment 5 May 2023

Background

When the instant proceedings came before the court, there had been 7 adjudications between

the parties arising from disputes under two projects (known as ‘Project Barberry’ and ‘Project Triathlon’, respectively) in which ISG had engaged FKC on similar bespoke sub -contracts. On Project Barberry there was the ‘Wood decision’, of February 2023, in which ISG was

found liable to pay FKC just under £1.7m (ISG having failed to serve a valid pay less notice

in response to FKC’s payment application). That was followed by the ‘Molloy decision’, of

April 2023, in which the adjudicator found that the gross value of the sub-contract works was

£3.7m (of which it was noted ISG had already paid around £2.8m leaving a balance of some

£900,000 ostensible due to FKC).

On Project Triathlon, there were three decisions dealing with various claims (the ‘Triathlon decisions’), the net effect of which was that FKC owed ISG some £67,000.

These proceedings were brought to enforce the Wood decision. Crucially no proceedings had

been commenced to enforce any of the other decisions.

ISG did not challenge the validity of the Wood decision but they argued that the court should

use its discretion to set off the sums due under the Wood decision against the net sum due to

ISG under the Triathlon decisions, and/or against the gross value of the works determined in

9

the Molloy decision. ISG said the net effect was that FKC was entitled to no more than

£900,000 for Project Barberry, less £67,000 due to ISG for Project Triathlon.

The Law

It was well- established that a party ordered to make payment under an adjudicator’s decision must usually pay in full, without deduction or set-off 9 as this would be contrary to the ‘pay now argue later’ policy of the Act. However , there were three limited exceptions:

(1) Where there was a contractual right set off provision that did not offend the statutory

requirement for immediate enforcement of an adjudicator’s decision ( Thameside

Construction v Stevens 10 ; BexHeat v Essex 11 ).

(2) Where it followed logically from the decision itself that a set off was permitted, for

instance where it was found that an overall amount was due but there was no order

for payment.

(3) In ‘an appropriate case and at the discretion of the court’, where there were two valid

adjudication decisions involving the same parties, the effects of which was that

monies were owed by each party to the other ( HS Works v Enterprise Managed

Services 12 ).

ISG argued that this case fell within the third limited exception. The court therefore looked

at the decision in HS Works , where the judge formulated four steps to be considered in

determining whether to set off two adjudicators’ decisions : • Step1, was to determine whether both decisions were valid. • Step 2, if both decisions were valid, they were capable of being enforced.

9 Ferson Contractors Ltd v Levolux AT Ltd [2003] BLR 118 .

10 Thameside Construction Co Ltd v Stevens [2013] EWHC 2071.

11 BexHeat Ltd v Essex Services Group Ltd [2022] EWHC 936 (TCC).

12 HS Works Ltd v Enterprise Managed Services Ltd [2009] EWHC 729 (TCC).

10

• Step 3, if both decisions were valid and enforceable, the court should enforce or give

effect to them both, provided that separate proceedings had been brought by each

party to enforce each decision.

• Step 4, the court should decide how each decision should be enforced. It might, for

example, be inappropriate to set off a second decision against the first, if the first

decision was made on the basis that there could be no set off.

The decision

The court found the facts of HS Works to be far removed from the present case. The court

had not been asked to determine the validity or enforceability of either the Molloy decision

or the Triathlon decisions and there were no separate proceedings to enforce those decisions.

The result was that the court had no discretion to permit set off in respect of any of those

decisions. Even if the court was wrong in that conclusion, there were other reasons why it

would not have exercised its discretion in favour of allowing a set off. These included the

fact that the Wood decision did not indicate that there could be set off or withholding against

the sum found due to FKC. And no actual payment had been found due under the Molloy

decision which was concerned with the gross value of the work. On the wider question of

whether an adjudicator’s decision relating to one project could be set off against a decision relating to another project, the court commented that this was ‘a point of some interest’,

which it was unnecessary to determine in the present case.

Accordingly, FKC was entitled to summary judgment for the full sum due under the Wood

decision.

Repayment following final determination

ISG Retail Limited v FK Construction Limited [2023] EWHC 2012 (TCC) Adrian

Williamson KC judgment 2 August 2023

11

This case is a sequel to the enforcement of the ‘Wood decision’ referred to above. Following the enforcement of the Wood decision, ISG commenced a further adjudication before Mr Molloy seeking a determination of the gross value of FKC ’s works. On 14 April 2023, Mr Molloy issued a Decision (the ‘ Molloy decision ’ ) in which he held, so far as relevant, that the

gross valuation of FKC's Works at 28 February 2023 was £3,736,679.72. On the same day,

ISG issued the present proceedings for a declaration that FKC was entitled to no more than the

sum found due by the Molloy decision and repayment of any sums paid in excess of that sum

and, by subsequent amendment, repayment of the sum of £1,751,063.70 paid to FKC by ISG on 16 May 2023 (the ‘ Wood Overpayment’ ).

ISG relied upon the decision of the Supreme Court in Aspect Contracts (Asbestos) Ltd v

Higgins Construction Plc 13 in which Lord Mance observed:

" 23. In my view, it is a necessary legal consequence of the Scheme implied by the 1996 Act into

the parties' contractual relationship that Aspect must have a directly enforceable right to

recover any overpayment to which the adjudicator's decision can be shown to have led, once there has been a final determination of the dispute…

It seemed to the learned judge that, where the dispute referred to an adjudicator had then been

referred to the Court or arbitration, and a different, final, outcome arrived at, it must follow that

any sums paid over pursuant to the decision of the adjudicator should be repaid. The

temporarily binding effect of the (incorrect) decision must yield to the final effect of the (ex

hypothesi) correct judgment. The effect of the earlier judgment on 14 June (in these

proceedings) was to undermine the basis on which Mr Wood proceeded and to reverse the

Wood decision, which could now be seen to be wrong.

In the result, ISG was entitled to the declarations sought in respect of, and summary judgment

for the repayment of, the sum of £1,751,063.70.

About the author:

13 [2015] 1 WLR 2961

12

Kenneth Salmon MCIArb is a qualified solicitor in England, Wales and Eire.

He is a Ciarb qualified and CMC accredited Mediator and Chair of

Education at Ciarb North West Branch. Kenneth is a construction specialist

currently working as a consultant to Slater Heelis Limited. He has extensive

experience of all forms of dispute resolution including arbitration,

adjudication, expert determination and mediation He is the author of Cases

on the Enforcement of Construction Adjudication Awards (2012) and the series Cases (on adjudication enforcement) published in Ciarb’s journal Arbitration: The International Journal of Arbitration, Mediation and Dispute

Management 1999-2017.

Read more about our work in adjudication.

If you want to develop your knowledge and skills in construction

adjudication, look at our training courses.

Find out more about how to apply to Ciarb's Adjudication Panel.

13

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 12 Page 13

Made with FlippingBook Online newsletter maker