Class 1 (-5/+10%)
Class 2 (-10/+15%)
Class 3 (-15/+20%)
1
Class 4 (-20/+30%)
2
Class 5 (-30/+50%)
25
Stage Review Count (Q1 2024)
Estimate classes and acceptable ranges vary across the NEOM Plan of Work stages with the expected accuracy increasing as the design advances. The below table shows the accuracy and class across the various stages of the NEOM Plan of Work.
STAGE 2 Masterplans Pre-concept Design, IABs: Class 5 (-30% / +50%)
STAGE 3A Concept Design: Class 4 (-20% / +30%)
STAGE 3B Developed Design: Class 3 (-15% / +20%)
STAGE 3C Detailed Design: Class 2 (-10% / +15%)
STAGE 3D Tender and Issued For Construction: Class 1 (-5% / + 10%)
Deviation to NEOM Plan of Work: A total of 27 deviation requests were processed in Q1 2024, all related to the NEOM Plan of Work Stages as follows:
Plan of Work
16
3
Codes & Standards
7
1
BIM Requirements
0
Other Technical Requirements
0
Approved
Rejected
Deviation Requests by Type (Q1 2024)
15% of deviation requests received in Q1 2024 were not approved due to a lack of justification and mitigation measures.
ETSD QUARTERLY REPORT | Q1 2024