For the deviation requests related to the NEOM Plan of work, the distribution per stage is as follows:
1 1%
2A 2%
2B 1% 2C 5%
3D 8%
2D 3%
3C 28%
3A 21%
3B 31%
Most deviation requests received target deviations across Stages 3A-3D to expedite the design development process to meet schedule constraints. Deviation Requests Distribution by NPoW Stages
In quality, the Q1 2024 PQI was 91%, higher than the cumulative of 87% and the target for compliance of 85%. PROJECT & VENDOR QUALITY MANAGEMENT