NEOM ETSD Quarterly Report Q1 2024

For the deviation requests related to the NEOM Plan of work, the distribution per stage is as follows:

1 1%

2A 2%

2B 1% 2C 5%

3D 8%

2D 3%

3C 28%

3A 21%

3B 31%

Most deviation requests received target deviations across Stages 3A-3D to expedite the design development process to meet schedule constraints. Deviation Requests Distribution by NPoW Stages

In quality, the Q1 2024 PQI was 91%, higher than the cumulative of 87% and the target for compliance of 85%. PROJECT & VENDOR QUALITY MANAGEMENT

60

70

75

80

85

90

95

100

Non-Compliant

Need Improvment

Compliant

Cumulative (87%)

Q1 2024 (91%)

Overall PQI