86% 60% 65% 70% 75% 80% 85% 90% 95% 100% Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 89% 89% 89% 88% 88% 89% 90% 90% 91% 91% 91% 60% 65% 70% 75% 80% 85% 90% 95% 100% Apr-23 May -23 Jun-23 Jul-23 Aug-23 Sep- 23 Oct-23 Nov- 23 Dec-23 Jan-24 Feb- 24 Mar-24 86% 89% 89% 89% 88% 88% 89% 90% 90% 91% 91% 91% Q1 2024 showed excellent overall performance, with a 91% PQI for each of January, February, and March.
Non-Compliant
Need Improvement
Compliant
Monthly Average
Overall Historical Monthly PQI
158,289 inspections were received in Q1 2024, out of which 147,866 were project work inspections and 10,423 were material-related. The approval rate of Work and Material Inspections stood at 77% and 81% respectively.
Work Inspection Requests (WIR) 2024
RECEIVED (Q1 2024)
UNDER REVIEW (Q1 2024)
APPROVED (Q1 2024)
REJECTED (Q1 2024)
77%
147,866
4,911
110,724
32,231
Material Inspection Requests (MIR)
RECEIVED (Q1 2024)
UNDER REVIEW (Q1 2024)
APPROVED (Q1 2024)
REJECTED (Q1 2024)
81%
1,848
10,423
593
7,982
Currently, 4 out of 47 batching plants and 1 out of 23 third-party labs are classified as high-risk and are not approved for use.
10 12 14 16
10 15 20 25 30 35
32 32
14 14
8 8
0 2 4 6 8
11
11
4 4
0 5
1 1
Low Risk
Medium Risk
High Risk
Low Risk
Medium Risk
High Risk
Batching Plants
3 rd Party Labs
ETSD QUARTERLY REPORT | Q1 2024