NEOM ETSD Quarterly Report Q1 2024

86% 60% 65% 70% 75% 80% 85% 90% 95% 100% Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 89% 89% 89% 88% 88% 89% 90% 90% 91% 91% 91% 60% 65% 70% 75% 80% 85% 90% 95% 100% Apr-23 May -23 Jun-23 Jul-23 Aug-23 Sep- 23 Oct-23 Nov- 23 Dec-23 Jan-24 Feb- 24 Mar-24 86% 89% 89% 89% 88% 88% 89% 90% 90% 91% 91% 91% Q1 2024 showed excellent overall performance, with a 91% PQI for each of January, February, and March.

Non-Compliant

Need Improvement

Compliant

Monthly Average

Overall Historical Monthly PQI

158,289 inspections were received in Q1 2024, out of which 147,866 were project work inspections and 10,423 were material-related. The approval rate of Work and Material Inspections stood at 77% and 81% respectively.

Work Inspection Requests (WIR) 2024

RECEIVED (Q1 2024)

UNDER REVIEW (Q1 2024)

APPROVED (Q1 2024)

REJECTED (Q1 2024)

77%

147,866

4,911

110,724

32,231

Material Inspection Requests (MIR)

RECEIVED (Q1 2024)

UNDER REVIEW (Q1 2024)

APPROVED (Q1 2024)

REJECTED (Q1 2024)

81%

1,848

10,423

593

7,982

Currently, 4 out of 47 batching plants and 1 out of 23 third-party labs are classified as high-risk and are not approved for use.

10 12 14 16

10 15 20 25 30 35

32 32

14 14

8 8

0 2 4 6 8

11

11

4 4

0 5

1 1

Low Risk

Medium Risk

High Risk

Low Risk

Medium Risk

High Risk

Batching Plants

3 rd Party Labs

ETSD QUARTERLY REPORT | Q1 2024