PROJECT SPOTLIGHTS
Bermondsey Block D, E + F Client: McAleer & Rushe / McLaren Sector: Residential Location: Bermondsey, London Value: £5.6m + £5.8m Scope: Partitions & Ceilings At Bermondsey D&E, part of The Bermondsey Project, Errigal began works in June 2025 delivering partitions and ceilings for 225 apartments and workspace, due for completion in 2027. At Bermondsey Block F, works started in October 2025 on 230 homes, covering partitions, MF ceilings and internal fit-out across a 64- week programme.
High Point Village Client: Ballymore Sector: Residential Location: London Value: £5.5m Scope: External Cladding Remediation
Errigal mobilised in March 2025 and began recladding works in April, with completion scheduled for August 2026. This is the first façade project to go through the BSR-controlled Gateway process and received a positive HSE report with zero comments or incidents. We are working closely with the facilities team while operating across all five occupied blocks.
Gatwick Airport, Pier 6 Western Extension Client: Mace Sector: Aviation Location: Gatwick, London Value: £8m Scope: External Envelope - façade and roof
The Project compromises building a two-storey extension to Pier 6 with eight new aircraft gates. Errigal are responsible for the design, supply and installation of the complete façade and roofing packages - comprising stick curtain walling, insulated metal panel cladding, secondary support steelwork, parapets/cappings and weathering details, full roofing systems and membranes.