From: concept to construction PROJECT STUDY The Naperville hotel exterior wall system provided by MagBoard /ROK-ON Building Systems.

Presentation produced by:

Manufacturer & Distribution Partner

ENERGEO Construction Solutions, LLC. Office: 850-625-3061

mail: info@energeoconstructionsolutions.com web: www.energeoconstructionsolutions.com

This presentation is provided as a reference guide to products and building system capabilities.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Hilton ®

Embassy Suites Hotel

Naperville, Illinois Completed Q1 2015

• Structural Insulated Sheathing building system installation • 168 Suite 7-story hotel with convention center • Factory Construction Prefabricated • Prefinished wall system panels • Wall panel installation 9/27/14 – 12/05/14

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Hilton ®

Embassy Suites Hotel

Naperville, Illinois Completed Q1 2015

SCOPE In - Factory Work  Panel & Frame design engineering  Manufacture:  MgO Structural Sheathing Panels  Cold formed 20 gauge steel frame  Integrate panel & steel assembly  Water Proof exterior  Apply Stucco Flex - exterior finish  Install Windows

ENHANCED FEATURES

 Rot resistant

• Fire resistant

 Termite resistant

• Mold resistant

 Water resistant

• Impact resistant

 Snow load resistant

• Airborne storm resistant

Manufacturing process 60 days/55,000 sq. ft. avg. 1,000 panels per day

Field Assembly Work • Panel attachment to red iron frame • Seal connection joints • Avg. install time per panel (15 mins) • Joint sealing time per panel (10 mins) FULLY TESTED PERFORMANCE

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

BACK VIEW

FEATURES

BENEFITS

ATTACHES TO THE STUDS LIKE REGULAR SHEATHING

USE COMMON TOOLS/FASTENERS. NO SPECIAL TRADES

Urethane caulking on outside of top and bottom tracks or foam gasket between track and panels

FEWER LAYERS, LESS STEPS THAN MOST COMPETING SYSTEMS DIRECT APPLICATION OF FINISHES . ROK-ON™ IS A SCREW BASE

FEWER SUBS, QUICKER OCCUPANCY

A foamboard adhesive is used at all joints to bond the panels together and provide a water resistant barrier

NO ADDT’L LAYERS NEEDED TO PROTECT IT ARCHITECTURAL FLEXIBILITY

ROK-ON™ Panel 12mm MAGBOARD™ facing outside and 6mm MAGBOARD™ facing inside Typical steel frame 16” O.C.

FEWER INSPECTIONS

ALL JOINTS FORWARD FACING

Drywall installed according to product specifications and installation guidelines

DEWPOINT MOVES OUTSIDE THE WALL CAVITY

NO CHANCE FOR WATER TO ENTER ENVELOPE

Starter Strip / Fire Stop

BETTER PERFORMANCE THAN COMPETING SYSTEMS AT SIMILAR COST

LOWER LONG-TERM OPERATING AND MAINTENANCE COSTS FEWER CALL BACKS

3” wide 12mm MAGBOARD™ strip placed with Peel and Stick and T-nailed or stapled in place 8” O.C. to seal the seam and fire protect the joint.

Urethane caulking on outside of top and bottom tracks of foam gasket between track and panels

Minimum on inch polyurethane insulation air barrier system to seal and strengthen the wall assembly. Actual insulation will be according to design specifications

Back View

(see fastener specifications)

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

 Panel Manufacturing  Frame Fabrication  Panel to Frame Assembly  Exterior Water Proofing  Exterior Coatings  Window Placement

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Premanufact ured Wall Assemblies

Premanufact ured Wall Assemblies

Premanufactured Wall Assemblies Steel Joint Details

Premanufactured Wall Assemblies Joint Details

St eel Joint Det ails

Assembly Joint Det ails

MagBoard Rim Board

MagBoard Rim Board

3" x 1' 20 Ga Galvanized Steel Strip . 1/4" gap between strips Screwed @ 2" with # 8 coarse thread self drilling screws.

PVC Corner Bead

8" Fiberglass Mesh.

Cementitious Base Coat.

Cement itious Base Coat. Runs on top of Steel Strips.

PVC Corner Bead

ROK-ON Panel

Low Expansion Polyurethane Spray Foam

Elastomeric Top Coat

MagBoard Rim Board

3/4" Backer Rod

12mm x 5" MagBoard Strip Stapled on back.

Polyurethane Caulk

Peel And Stick Membrane

PL-300 Foam Adhesive

PVC Corner Bead

Acrylic Caulk

Cementitious Base Coat.

3" x 1' 20 Ga Galvanized Steel Strip

Elastomeric Top Coat

Air/Water Barrier rolled on under Steel Strips.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

For demonstration purposes only. Actual details will be according to architectural and engineering specifications.

 Red Iron Steel Frame  No scaffolds required  Attachment from interior  Seal exterior joints

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Revenue, Profit and Productivity Opportunities

Time Lapse Video

 Longer lifecycle building

Climate resilient

More durable materials

 Shorter construction cycle

Less construction cost

 Quicker occupancy -------------------------------------- Reduced operating cost Reduced maintenance cost

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Benefits for the GC / Builder

 Can be constructed and pre-finished in a modular environment. Better quality control.

Large potential labor savings. • Less steps means lower labor costs to install relative to competing systems. • With modular construction, able to convert $85/hr. union labor to $20/hr. factory cost. (example)

Traditional EIFS system

 Does not require scaffolding to install. (Hidden cost savings)

 Reduce construction cycle by weeks / months. • Can lead to better ROI. • Allows flexibility in “critical path” timelines.

SIS™Modular System Parapet walls being installed

 The system performance leads to fewer call-backs and maintenance.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Benefits for the Building Owner

2013 Hotel Occupancy Statistics

Other Benefits

Better energy performance leading to reduced energy costs over time.

Lower overall maintenance costs.

Competitively priced to EIFS, (among the lower cost alternatives) with much better performance.

Source: STR Global Statistics – March 2013

 Less steps directly allows for quicker occupancy for the building owner.

Architectural flexibility in design.

 For a full-service hotel, getting in just 60 days early can mean an additional $882,240 in profit!

Tremendous fire performance.

 This more than pays for the entire building envelope.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Benefits for the Architect

 Completely developed exterior wall system that can help the

architect provide their client with a superior building envelope at a price that is among the lowest cost alternatives in the marketplace.

 The system can take weeks or months off the construction cycle leading to earlier occupancy. The increased revenue can actually help offset the cost of the envelope leading to a lower overall cost and better ROI for the client.  The system exceeds the 2015 ICC IBC and IRC codes, with superior performance. Fully tested to meet all of the applicable building codes in North America.

Osaka – Pier Park

Embassy Suites -Naperville

 Design flexibility. ROK-ON™ can accept most exterior finishes with little or no modification to existing plans.

 Significant projects are already in place that allow proof of concept. Passed the test of the owner, architect, builder, and code officials. • These include brands like Hilton®, Holiday Inn®, the Dept. of Defense, and others. • Proven Financial models are available • Completely developed details are available

Holiday Inn - Mexicali

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Benefits for Prefabrication

ROK-ON (SIS)™ is perfect for prefabrication of external wall assemblies.  Modular projects often include only the frame and sheathing. The balance of the wall is finished in the field.  ROK-ON (SIS)™ replaces several layers of a typical wall assembly in one product, that is installed in about the same time as the first layer of sheathing.

 Productivity is increased as the time to construct a wall assembly is substantially reduced.

• ROK-ON (SIS)™ is attached to the frame using conventional tools. • No special requirements. • Additional steps to install the vapor barrier or the exterior continuous insulation are not required. • The panel can be finished directly, reducing even more layers like wire mesh and multiple applications for stucco.

Fewer steps means less time in the construction cycle which equals greater productivity. It also means less labor and space is required to complete the tasks.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Benefits for the Modular Builder

Along with the increased revenue and margin potential, productivity is also significantly increased adding further to the profitability of the system for a modular builder.  Installation of the entire wall system is achieved in about the same time as the first layer of sheathing in traditional assemblies.

 Additional steps to install the vapor barrier or the insulation are not required.

 Since the panel is a screw base and can be finished directly, even more layers can be reduced – like wire mesh for stucco.  Fewer steps means less time in the construction cycle – greater productivity. It also means less labor is required to complete the tasks .

PANELS PRODUCED IN MAGBOARD - OWNED FACTORY

BETTER, FASTER, COST EFFECTIVE, and HIGHER PROFITABILITY

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

MgO Board Qualifications

 All of our products are fully tested by Intertek to meet the 2015 edition of the IBC codes. 53 separate ASTM tests completed.

 We own and operate our own manufacturing plants with significant capacity to meet growth needs.

 Each plant facility utilizes a fully integrated quality control process administered by Intertek.

 We proudly stamp all of our products with the Warnock-Hershey stamp and are listed with Intertek on their “Spec Direct” site for our boards and panels. ( www.spec-direct.com )

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

SIS™ Qualifications

 We have passed the due diligence with architects/engineers, building code officials, GC’s, and owners, on our current projects going up.

 We provide in-house engineering and technical support with both a structural engineer and architect on staff.  WARRANTY - 20-years when installed according to mfg. guidelines.  $10 million per-occurrence product liability insurance.

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

Hilton ®

Embassy Suites Hotel

Naperville, Illinois Completed Q1 2015

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

LARGE BUILDING PROJECT STUDY

Hilton ®

Embassy Suites Hotel

Naperville, Illinois

Presentation produced by:

Product Testing & Certifications (Click on booklet image)

Manufacturer & Distribution Partner

ENERGEO Construction Solutions, LLC. Office: 850-625-3061

mail: info@energeoconstructionsolutions.com web: www.energeoconstructionsolutions.com

ROK-ON, Naperville Hotel Presentation Document ID: NH08R0517

California| Florida |Georgia| Texas

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 12 Page 13 Page 14 Page 15 Page 16 Page 17 Page 18

Made with FlippingBook Online document