January 18, 2021 Directors Report.

Facilities Manager Report January 12, 2021 By Byron Jessie – Facilities Manager

Front entry fountains: The west side front entry fountains once again are to their correct height. We had to make a slight adjustment to the venturi aeration nozzles so that they would be slightly above the newly established water level.

Satellite fencing: I am currently in the process of getting bids to replace certain sections of the wrought iron fencing at each satellite. As you can see in the attached picture there is rusting that has developed at the base and has caused the fencing to become unstable. Each satellite has the happening to some degree and the replacement is considered in the reserve study. So far, the bids are below what was budgeted.