MBA280 Class Projects Flipbook Spring '25

Sensitivity Analysis & Risk Mitigation

Scenarios

Mitigations

Key Variables

• Cost +10%: IRR drops to 18% • Rent -10%: IRR drops to 20% • Cap rate +0.5%: IRR drops to 19%

• Fixed-price modular contracts • Pre-leasing to top employer groups • CPACE reduces WACC

Construction cost, rent, cap rent

Levered Return (IRR)

Levered Return (IRR)

Constructi on Loan Interest Rate (%)

Constructio n Cost ($/psf)

9.8% 5.0% 5.5% 6.0% 6.5% 7.0%

0.0%

300

325

350

375

400

4.5%

20.8% 20.5% 20.2% 20.0% 19.7%

4.5%

24.3% 22.2% 20.2% 18.4% 16.8%

4.0%

19.6% 19.4% 19.1% 18.9% 18.6%

4.0%

23.2% 21.1% 19.1% 17.3% 15.7%

3.5%

18.5% 18.3%

18.0%

17.7% 17.5%

3.5%

22.1% 19.9%

18.0%

16.2% 14.6%

3.0%

17.4% 17.1% 16.8% 16.6% 16.3%

3.0%

21.0% 18.8% 16.8% 15.1% 13.4%

2.5%

16.2% 15.9% 15.7% 15.4% 15.2%

2.5%

19.8% 17.6% 15.7% 13.9% 12.3%

Contingen cy (%)

ESG Initiative ($)

0.0% 3.0% 3.5% 4.0% 4.5% 5.0%

4,000,000 4,500,000 5,000,000 5,500,000 6,000,000

4.5%

20.5% 20.4% 20.2% 20.1% 19.9%

4.5%

20.4% 20.3% 20.2% 20.2% 20.1%

4.0%

19.4% 19.3% 19.1% 19.0% 18.8%

4.0%

19.3% 19.2% 19.1% 19.0% 19.0%

3.5%

18.3% 18.1%

18.0%

17.8% 17.7%

3.5%

18.1% 18.1%

18.0%

17.9% 17.9%

3.0%

17.1% 17.0% 16.8% 16.7% 16.5%

3.0%

17.0% 16.9% 16.8% 16.8% 16.7%

2.5%

16.0% 15.8% 15.7% 15.5% 15.4%

2.5%

15.8% 15.7% 15.7% 15.6% 15.5%