Table 7-3 | Roadway Prioritization Prioritization Level - High Ligon Mill Road S Main Street to Reynolds Mill Road

1 2 3

Roadway Widening

Roadway Widening & Grade Separation

Ligon Mill Road Pompeii Place to Steeple Run Drive Rogers Branch Road Rogers Road to Forestville Road Rogers Road S Main Street to Heritage Branch Road

Roadway Extension & Widening

Roadway Widening & Grade Separation

4

Prioritization Level - Medium Burlington Mills Road US 1 to Town Limits

5 6 7

Roadway Widening

Harris Road US 1 to N Main Street

Roadway Widening

Roadway Extension & Grade Separation

Harris Road Extension N Main Street to Royal Mill Avenue Hwy 98 Stone Park Drive to Town Limits Ligon Mill Road Extension Stadium Drive to Hwy 98 Rogers Road Rogers Branch Road to Town Limits

8 9 10 11 12 13 14 15 16 17 18

Roadway Widening

Roadway Extension

Roadway Widening

Prioritization Level - Low Averette Road

Roadway Widening

Oak Grove Church Road to Hwy 98 Chalk Road Jones Dairy Road to Town Limits

Roadway Widening

Durham Road US 1 to S Wingate Street Forestville Road Rogers Road to Town Limits

Roadway Widening

Roadway Widening

Friendship Chapel Road S Main Street to Holding Village Way

Roadway Widening

Heritage Lake Road Hwy 98 to Rogers Road

Roadway Widening

Hwy 96 Oak Grove Church Road to Hwy 98

Roadway Widening

Jones Dairy Road Hwy 98 to Town Limits

Roadway Widening