28-HOME SUBDIVISION PROJECT UPDATE AND COMMUNITY FEEDBACK
SUMMARY OF COMMUNITY FEEDBACK: Phase 1 - Feedback period: March 21, 2024 - April 2, 2024
WORK COMPLETED
•Survey drawings
HOMES: • Accessibility • Senior housing
•Land encumbrance check
•Kick-off meeting with sub-consultants
•Environmental assessment report
•Home additions (i.e. workshop, deck expansion) • Rental, or if there will be the option to purchase
•Geotechnical report
•DAR Application (funding request for design stage)
WATER SUPPLY: • Amount of water to supply all the homes
• Site clearing
• Preliminary subdivision design
WATER SYSTEM SUSTAINABILITY AND MAINTENANCE: • Design of the system for long-term sustainability • Training and personnel needed for maintenance
•Community open house (March 21)
NEXT STEPS
•Detailed subdivision design (target completion - May 2024)
SUBDIVISION SITE I Nuuautin 28-Home Subdivision Project
•Septic design and report
•Construction cost estimate
• Civil construction drawings
•Commence water servicing and infrastructure design,
and electrical infrastructure design
•PAR Application (funding request for construction stage)
LYTTON FIRST NATION STEIN WATER SYSTEM IMPROVEMENT PROJECT WWW.APLINMARTIN.COM/LFNWATERSYSTEM OPENHOUSE@APLINMARTIN.COM