PROJECT STATISTICS AND CURRENT STATUS
ALKALI ROAD ACCESS I Nuuautin 2B Subdivision
•Locations of the water system upgrades: Nuuautin IR 2, 2B, 21, and Kleetlekut IR 22.
The Stein Water System expanse is on West and East side of the Fraser River.
Subdivision Site
•Pump station upgrades will be located within Stryen 9, and Inkluckcheen 21
•Access to the subdivision: Alkali Road and Green Meadows Road. •The Water System will exceed the ISC requirements for fire storage and meet
the Fire Underwriters Survey (FUS) specifications of 67 L/s for 1.5 hours for single-
family homes, and 117 L/s for 2 hours for institutional buildings (specifically at the
new Stein Valley Nlakapamux School).
Alkali Road Access
•The Water System is projected to support population growth for 20 years.
•This is based on growth projections from Indigenous Services Canada’s
ALKALI ROAD ACCESS I Nuuautin 2B Subdivision
Indigenous Statistics and Research Unit.
NEXT STEPS •Community Open House Feedback
WORK COMPLETED
Alkali Road will receive a full upgrade to align with the Ministry of Transportation and Infrastructure standards.
•Environmental Assessment Report
•Detailed Stein Water System Design
•Geotechnical Report
•PAR Application (funding request for
• Survey Drawings
the construction stage)
•DAR Application (Funding request
Grading to accommodate the new Alkali Road upgrade.
•Cost Estimate
for the design stage)
•Contract Tender and Award
•Preliminary Water System Design
•Civil Construction Drawings
•Record Drawings
LYTTON FIRST NATION STEIN WATER SYSTEM IMPROVEMENT PROJECT WWW.APLINMARTIN.COM/LFNWATERSYSTEM OPENHOUSE@APLINMARTIN.COM