CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Facility Project Details

Project Name:

Restroom Renovations

This project will include the complete renovation of all recreation center and town center restrooms. This project will also include the addition of metal detectors in the entry doors on the west side of Town Center.

Project Description:

Fund: Estimated Start Date: Estimated Completion Date: Status: Operating Impact:

486

10/01/19 Ongoing Design is approximatley 90% complete. None

Estimated Expenditure (000's)

Revised: 10/30/20

PY Budgeted

FY

FY

FY

FY

FY

Total Estimated Cost

Project Name/No.

Amount

2020-21 2021-22 2022-23 2023-24 2024-25

$

-

$ 1,050

Restroom Renovations

$

425 $

625

$

-

$

-

$

-

$

-

$

-

$

-

$

-

$

-

$

-

$

-

Total:

$

-

$

425

$

625

$

-

$

-

$

-

1,050 $

Estimated Amount (000's)

Funding Sources

$

-

1,050 $

Transfer from General Fund 101

$

425 $

625

$

-

$

-

$

-

422