CITY OF DESOTO
Capital Improvement Program FY 2021- 2025 Street Project Details
Project Name/No: Project Description:
Parkerville Road Widening (Polk to Hampton Road)
Widen roadway to a 4-lane divided concrete roadway with underground drainage.
Estimated Start Date:
10/1/2022 9/30/2026
Estimated Completion Date:
Fund:
490
Currently Unfunded. November 2014 Bond Election passed. Anticipated issuance of General Obligation Bonds FY2022 thru 2026. Ongoing operational costs include irrigation, landscaping and lighting at approximately $25k per year.
Status:
Operating Impact:
ESTIMATED EXPENDITURES (000's)
Revised: 10/30/20
PY Budgeted
FY
FY
FY
FY
FY
Total Estimated Cost
Project Name/Number
Amount
2020-21
2021-22
2022-23
2023-24
2024-25
$
-
$
2,500
Parkerville Road Widening
$
-
$
-
$
1,000
$
-
$
1,500
Estimated Amount (000's)
Funding Sources
$
-
$
2,500
General Obligation Bonds
$
-
$
-
$
1,000
$
-
$
1,500
438
Made with FlippingBook - professional solution for displaying marketing and sales documents online