CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Street Project Details
Project Name: Project Description:
Danieledale Road (West CL - Westmoreland)
Widen roadway to 4-lane divided concrete roadway with underground drainage and typical amenities.
Estimated Start Date: Estimated Completion Date:
10/01/19 09/30/23
Fund: Status:
490
In Progress and paritally funded.
Ongoing operational costs include irrigation, landscaping and lighting at approximately $25k per year.
Operating Impact:
Estimated Expenditure (000's)
Revised: 10/30/20
PY Budgeted
FY
FY
FY
FY
FY
Total Estimated Cost
Project Name
Amount
2020-21
2021-22
2022-23
2023-24
2024-25
$
-
$
4,000
Danieledale Road (West CL - Westmoreland
$
-
$
1,500
$
2,500
$
-
$
-
Estimated Amount (000's)
Funding Sources
$
-
$
4,000
General Fund Transfers
$
-
$
1,500
$
2,500
$
-
$
-
440