CITY OF DESOTO

Capital Improvement Program FY 2021 - 2025 Street Project Details

Project Name/No: Project Description: Estimated Start Date:

Hampton Road Reconstruction

Construction of water, sewer and paving from Pleasant Run to Belt Line Rd

10/1/2018 9/30/2024

Estimated Completion Date:

Fund:

490

Status:

Funded. Ongoing operational costs include irrigation, landscaping and lighting at approximately $40k per year.

Operating Impact:

ESTIMATED EXPENDITURES (000's)

Revised: 10/30/20

PY Budgeted

FY

FY

FY

FY

FY

Total Estimated Cost

Project Name/Number

Amount

2020-21

2021-22

2022-23

2023-24

2024-25

$

1,500

$

5,500

Hampton Road Reconstruction

$

-

$

-

$

-

$

2,000

$

2,000

Estimated Amount (000's)

Funding Sources

$

1,500

$

5,500

Certificate of Obligation Bonds

$

-

$

-

$

-

$

2,000

$

2,000

445