Capital Improvement Program FY 2021 - 2025 Street Project Details

Project Name/No: Project Description:

County Joint MCIP #2 (Westmoreland Road)

Joint project with Dallas County to widen existing 2 lane arterial to 4-lane divided concrete street with underground drainage and sidewalks.

Estimated Start Date:

10/1/2017 9/30/2022

Estimated Completion Date:

Fund:

490

Currently Unfunded. Anticipated issuance of Certificates of Obligation FY2017 thru 2021. Ongoing operational costs include irrigation, landscaping and lighting at approximately $40k per year.

Status:

Operating Impact:

ESTIMATED EXPENDITURES (000's)

Revised: 10/30/20

PY Budgeted

FY

FY

FY

FY

FY

Total Estimated Cost

Project Name/Number

Amount

2020-21

2021-22

2022-23

2023-24

2024-25

$

1,000

$

7,000

$

2,000

$

2,500

$

1,500

$

-

$

-

County Joint MCIP #2 (Westmoreland)

Estimated Amount (000's)

Funding Sources

$

1,000

$

7,000

Certificate of Obligation Bonds

$

2,000

$

2,500

$

1,500

$

-

$

-

CO Bond proceeds to refund Chattey Road Project.