CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Drainage Project Details
Project Name/No.: Project Description:
Lake Grove
Replace voids around existing drainage culvert. Provide point and pavement repairs as necessary.
Estimated Start Date: Estimated Completion Date: Fund:
09/30/21 05/01/20
528
Status: Operating Impact:
Project delayed to FY 19 for design. No operating impact.
Estimated Expenditure (000's)
Revised: 10/30/20
PY Budgeted Amount
FY
FY
FY
FY
FY
Total Estimated Cost
Project Name/No.
2020-21 2021-22 2022-23 2022-23 2024-25
Lake Grove
$
-
$
-
$
-
$
-
$
473
$
473
Estimated Amount (000's)
Funding Sources
$
473
$
473
Fund 522-Drainage Utility Fund Transfer
$
-
$
-
$
-
$
-
$
-
458