CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Water Project Details
Project Name/No.: Project Description:
Hampton Pump Station Rehab
Evaluate efficiency of Hampton Pump Station and design/ construct/install additional pumps and electrical/building renovations.
Estimated Start Date: Estimated Completion Date: Fund:
03/01/21 09/30/23
508
Status: Operating Impact:
Design to begin in 2021 No operational impact.
Estimated Expenditure (000's)
Revised: 10/30/2020
PY Budgeted Amount
FY
FY
FY
FY
FY
$ 18,500 Total Estimated Cost
Project Name/No.
2020-21 2021-22 2022-23 2023-24 2024-25
$
-
$ 3,500 $ 7,500 $ 7,500
$
-
$
-
Hampton Road Pump Station Rehab
Estimated Amount (000's)
Funding Sources
$
-
18,500 $
Anticipated Certificate of Obligation Bonds
$ 3,500 $ 7,500 $ 7,500
$
-
$
-
466