DeSoto FY21----FY22-Approved-Budget

CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Water Project Details

Project Name/No.: Project Description:

Mixing and monitoring imrprovements as well as improvements to to Briarwood EST site's access gate. Briarwood Elevated Storage Tank Rehab and Site Imp

Estimated Start Date: Estimated Completion Date: Fund:

10/01/23 01/01/25

508

Status: Operating Impact:

No operational impact.

Estimated Expenditure (000's)

Revised: 10/30/2020

PY Budgeted Amount

FY

FY

FY

FY

FY

Total Estimated Cost

Project Name/No.

2020-21 2021-22 2022-23 2023-24 2024-25

$

-

$

150

$

-

$

-

$

-

$

150

$

-

Briarwood Elevated Storage Tank Rehab

Estimated Amount (000's)

Funding Sources

$

-

$

150

Anticipated Certificate of Obligation Bonds

$

-

$

-

$

-

$

150

$

-

472