CITY OF DESOTO Capital Improvement Program FY 2021 - 2025 Water Project Details
Project Name/No.: Project Description:
Chlorine Booster
Water distribution system will be evaluated to determine the best location(s) to add chlorine to the water purchased from Dallas Water Utilities. Once locations are identified, specifications for the chlorine equipment will be developed and a supply vendor identified to provide equipment on a pilot basis for evaluation. An equipment lease versus purchase option will also be evaluated.
Estimated Start Date: Estimated Completion Date: Fund:
09/25/17 06/01/20
508
Professional consultant has been selected. Pilot program anticipated to be online in late summer 2018. No operational impact
Status: Operating Impact:
Estimated Expenditure (000's)
Revised: 10/30/2020
PY Budgeted Amount
FY
FY
FY
FY
FY
$ 1,880 Total Estimated Cost
Project Name/No.
2020-21 2021-22 2022-23 2023-24 2024-25
$
880
$
-
$ 1,000
$
-
$
-
$
-
Chlorine Booster Project - CHLBOO
Estimated Amount (000's)
Funding Sources
$
880
1,880 $
Fund Balance
$
-
$ 1,000
$
-
$
-
$
-
479