OTHER PARTIES
QUANTITATIVE
QUALITATIVE
RISK RESPONSE
1. CONSTRUCTION MANAGER Will there be a construction manager? Has the construction manager’s role been adequately defined? Is the construction manager sufficiently qualified to undertake this role? 2. SPECIAL CONSULTANTS Are any special (e.g., geotechnical or abatement) consultants required? To the best of your knowledge, are these consultants capable? Are you accepting vicarious liability for these consultants? If so, are you appropriately compensated and protected?
3. OTHER
OVERALL OTHER PARTIES ASSESSMENT
FEE
QUANTITATIVE
QUALITATIVE
RISK RESPONSE
1. ADEQUATE FEE Is your fee adequate for the required services? Will it cover costs and provide a profit?
2. ADDITIONAL SERVICES Are there fee provisions for contingent additional services?
3. OTHER
OVERALL FEE ASSESSMENT
50 • From Risk to Profit - Benchmarking and Claims Studies