C+S October 2021 Vol. 7 Issue 10

Reinforced Earth | www.reinforcedearth.com

Low-density Cellular Concrete for MSE Wall Backfill in Hawaii

The H-1 Freeway in Oahu is the busiest roadway in the state of Hawaii. In 2019, Hawaii Department of Transportation completed improvements to H-1 through Pearl City, about ten miles northwest of Honolulu. The roadway surface was replaced with new pavement, and the shoulder lanes were widened. Two Reinforced Earth® mechanically stabilized earth (MSE) walls were installed along the highway on the existing slope to widen the road.

Aerial view of one of the completed MSE walls along the side of the roadway.

Both walls are 10 feet tall from foundation to roadway grade. Each wall added a length of highway shoulder about 500 feet long. The walls were built using concrete panel facing, steel soil reinforcements, and low-density cellular concrete (LDCC) for backfill. The existing foundation had bearing and settlement limitations. Even though the proposed walls were not signifi- cantly tall, a new MSE wall filling in the existing slope using granular soil or crushed stone backfill material would create too heavy of a new load for the foundation. Either the wall volume would have to be below a certain weight, or else the foundation would need improvement prior to installation of the wall.

To optimize project schedule and cost, the contractor, Kiewit, considered fac- tors such as the size of the walls, material availability, and installation speed. RECo’s engineering department did a calculation to show that the weight of the MSE wall volume with LDCC would be less than the original weight on the foundation with the original slope, resolving the bearing and settlement is- sues. Ultimately, the lightweight backfill option was chosen, using Cell-Crete’s LDCC. Thematerial had a unit weight of 36 lb per cubic-feet, which is about 70 percent lighter in weight than typical select granular backfill. Using LDCC for backfill requires a modified MSE installation process. A con- ventional MSE wall is built by repeating the process of compacting lifts of backfill, laying soil reinforcement on top of the fill, then compacting more fill on top. However, LDCC is poured as a liquid and requires that the soil reinforcements be located in the middle of a lift rather than at a joint in the LDCC lifts. This means that the soil reinforcements are supported off the ground using rebar stakes to make sure the LDCC flows below and above the soil reinforcements. Other measures must be taken to contain the LCC liquid pour, which is not necessary when using granular backfill. Once the LDCC cures, it results in a lightweight wall mass. The use of low-density cellular concrete for MSE backfill is becoming more common across the country as a solution for weak foundations, or even simply for project constructability. In the case of the H-1 Freeway widening, it proved to be the best alternative to produce a new lightweight embank- ment with the strength to carry the highest volume of traffic in Hawaii.

A lower row of soil reinforcements are shown installed above a lift of LDCC.

18

csengineermag.com

october 2021

Made with FlippingBook Annual report