Villa plotted development
18m main road opened for trac
Phase I (10 acres) – Infrastructure work fully completed along with landscaping
High rise buildings - North
Phase II (34 acres) – Infrastructure work fully completed along with landscaping
Buildings Wilton I & II and Windsor I & II – handed over to facility management services (FMS)
Podium level hardscaping & landscaping is completed and xing of the children’s play equipment & gazebos in progress
Villa residences
375 apartments handed over, 350 apartments occupied in The Highlands, North
3 luxury villas is under construction
The Willows
First coat of paint has been applied
Leasing Desk: To rent out your apartment, we have created a special leasing desk. You may get in touch with Mr. Viswam for the same via mail - pviswam@hrealty.com
High quality civic infrastructure in the form of roads, power, water, telecommunications & sewerage have been provided
High rise buildings - South
Township amenities
1 st stage of nishing work completed in all the towers namely Warwick I & II, Chartwell I & II, Chatsworth I & II, Clarendon I & II
A 30-bed hospital is now open for residents and public
A 14000 sq.ft. fully air-conditioned Auditorium / Convention center is ready for weddings, seminars, corporate o-sites and other activities
Tiles, marble, door shutter xing & painting work is in progress in Warwick I & II and Chartwell I & II
Mechanical, Electrical and Plumbing (MEP) work is in progress in all the towers
30+ sporting facilities operational
Lifts’ guide rail xing work is in progress