Overview for Year 3
• October 15 th
• ACC software Deployed to Target HW
• November 15 th
• Waivers & Reworks Complete
• December 15 th
• Controls Feature Freeze • HMI Integrated
• February 15 th
• Baseline ACC Track Testing Complete • Torque Path Cal Freeze
• March 1 st
• Lateral Feature in Simulation`
• April 15 th
• Drivability Cal Freeze • Baseline AIN Track Testing Complete
• May 1 st
• Lateral Feature Deployed to HW • Functional DMS (Standalone)