TVA Board Meeting - FY24 Financial plan and budget- Reso-Memo
Projects Greater than $200 Million – Initial Approvals
$ million
FY23 and Prior
Current Year's Project Total
Capital Expenditure Project
FY24
Capacity Expansion Allen Aeroderivative Combustion Turbines (CT)
$0.5
$244.3
$351.3
Cheatham County Energy Solution
$1.7
$118.9
$1,192.7
New Caledonia CT
$0.1
$48.4
$494.9
Kingston Energy Solution
$4.7
$441.6
$2,812.0
Clean Air
Shawnee Selective Catalytic Reduction – Units 2, 3, 7, and 8*
$106.4
$82.4
$240.4
* Timing of annual project spend is being evaluated as project plans are finalized.