TVA Board Meeting - FY24 Financial plan and budget- Reso-Memo

Projects Greater than $200 Million – Initial Approvals

$ million

FY23 and Prior

Current Year's Project Total

Capital Expenditure Project

FY24

Capacity Expansion Allen Aeroderivative Combustion Turbines (CT)

$0.5

$244.3

$351.3

Cheatham County Energy Solution

$1.7

$118.9

$1,192.7

New Caledonia CT

$0.1

$48.4

$494.9

Kingston Energy Solution

$4.7

$441.6

$2,812.0

Clean Air

Shawnee Selective Catalytic Reduction – Units 2, 3, 7, and 8*

$106.4

$82.4

$240.4

* Timing of annual project spend is being evaluated as project plans are finalized.