Commissioning planning:
Conceptual design,
detail design,
comm planning,
comm execution,
Initial operations
Start up
• Begin site Inspections of piping and equipment with P&IDs and • datasheets. • Electrical schematics. • This activity continues until the plant is mechanically complete. • Maintain Punch List of construction deficiencies. • Confirm vendor support and schedule for startup activities. • Deliver or coordinate Operator Training. • Update schedule and procedures as necessary.