Commissioning planning:

Conceptual design,

detail design,

comm planning,

comm execution,

Initial operations

Start up

• Begin site Inspections of piping and equipment with P&IDs and • datasheets. • Electrical schematics. • This activity continues until the plant is mechanically complete. • Maintain Punch List of construction deficiencies. • Confirm vendor support and schedule for startup activities. • Deliver or coordinate Operator Training. • Update schedule and procedures as necessary.