Our Community
North Campus
22 Buildings
• • •
40k+ ft2 photovoltaics;
Under construction + PV
37 EV charging stations with total 62 ports; 105 MW Combined heat and power plant & co-located central chiller plant; Wind power purchase agreement (50 MW); Two existing chiller plants; Ground-source heat pump plant.
steam and chilled water plant
105MW Combined Heat and Power (CHP) plant
•
•
PV
West Campus
East Campus
Chiller plant
• •
Ground source heat pump bunker
EAIC: Energy Advancement and Innovation Center