Big Picture Timeline – 5 Year Project Horizon
March ’22 Jan ’24
Oct ’24 Nov ’25
June ’26
Nov ’27
Conduct initial assessments, develop appropriate plans, secure necessary approvals to future project work, install sensing equipment, characterize buildings and DERs, and establish baselines
Validate a model of the CC, and use it to identify control strategies, conduct distribution-level risk assessments, and pilot control strategies in a single building
Installation of all communication & actuation hardware for control of the CC, CC- wide control w/ manual approval, and pilot automatic control in a single building
Execute, assess and refine automatic control for the entire CC
Conduct final analyses and create recommendations for market transformation, regulatory policy, Smart Institutions business model, and CC operation. We will also hold an Expo to disseminate results