CAR External Advisory Board Presentation, Spring, 2023

Big Picture Timeline – 5 Year Project Horizon

March ’22 Jan ’24

Oct ’24 Nov ’25

June ’26

Nov ’27

Conduct initial assessments, develop appropriate plans, secure necessary approvals to future project work, install sensing equipment, characterize buildings and DERs, and establish baselines

Validate a model of the CC, and use it to identify control strategies, conduct distribution-level risk assessments, and pilot control strategies in a single building

Installation of all communication & actuation hardware for control of the CC, CC- wide control w/ manual approval, and pilot automatic control in a single building

Execute, assess and refine automatic control for the entire CC

Conduct final analyses and create recommendations for market transformation, regulatory policy, Smart Institutions business model, and CC operation. We will also hold an Expo to disseminate results