Clean Air Industries WeldStation EVO User Manual

I NSTALLATION

The WeldStation requires some minor assembly.

A standard unit will come with an exhaust cover pre-installed.

The unit and a booth are integrated into a single machine referred to as the 'main unit'.

A secondary booth can be attached to the main unit and creating a "Dual WeldStation". If no

secondary booth is used, then the main unit is referred to as a "Single WeldStation".

See the 'WeldStation Accessories User Manual' for accessory assembly instructions.

G ENERAL I NSTALLATION G UIDELINES

Clean Air America’s WeldStation units are shipped via freight and generally arrive on a flat bed trailer.

The main units are partially crated, on a pallet, and are shipped lying on their sides. The secondary

booths are partially crates and shipped upright. Use a fork lift truck, driven by a qualified individual, to

remove the crate / pallet from the truck. Occasionally, fork extensions are helpful.

Once the WeldStation unit is inside the facility, ready to be uncrated, please proceed

cautiously. Banding straps and plastic wrap must be removed.

WeldStation units are heavy and tend to

be top heavy. The motor and the majority

of the metal are located at the top of the

unit. Please see the "Unit Weight" section

for proper weights.

There are (4) steel plate eyelets vertical at

the top of unit. These are the lifting lugs.

There are (9) floor mounting holes on the

bottom flange of the unit