I NSTALLING THE F LAT G ASKET ON THE U NIT
Flat Gasket must be places around the outside of the plenum
opening before assembly. This should only be done around the
opening being mated to the secondary booth.
The flat gasket must be cut to length from the roll.
For each opening, the following pieces should be cut (2) 19" long,
and (2) 25" Long.
The 19" long pieces are placed above and below
the opening. These will cover all (3) bolt holes above the opening
and all (3) bolt holes below the opening.
The 25" long pieces are placed on the sides of the
opening. These gasket pieces will be between the upper and lower
gasket pieces and will cover the (2) bolt holes on each side of the
opening.
The (4) gasket pieces must be placed centered
over the bolt pattern.
Once all four flat gasket pieces are placed, there
should be no gap between the gaskets.
Once all four flat gasket pieces are placed, then
punch a hole into the gasket at each bolt hole to allow a bolt to
pass through. Be careful not to damage the gasket.