Clean Air Industries WeldStation EVO User Manual

I NSTALLING THE F LAT G ASKET ON THE U NIT

Flat Gasket must be places around the outside of the plenum

opening before assembly. This should only be done around the

opening being mated to the secondary booth.

The flat gasket must be cut to length from the roll.

For each opening, the following pieces should be cut (2) 19" long,

and (2) 25" Long.

The 19" long pieces are placed above and below

the opening. These will cover all (3) bolt holes above the opening

and all (3) bolt holes below the opening.

The 25" long pieces are placed on the sides of the

opening. These gasket pieces will be between the upper and lower

gasket pieces and will cover the (2) bolt holes on each side of the

opening.

The (4) gasket pieces must be placed centered

over the bolt pattern.

Once all four flat gasket pieces are placed, there

should be no gap between the gaskets.

Once all four flat gasket pieces are placed, then

punch a hole into the gasket at each bolt hole to allow a bolt to

pass through. Be careful not to damage the gasket.

Page 26 of 83

1-866-665-1829

clean-air.com

sales@clean-air.com

Made with FlippingBook - professional solution for displaying marketing and sales documents online