Clean Air Industries WeldStation EVO User Manual

If the spark baffles are already

installed, remove them. See the

'Removing the Spark Baffles' section

of the user manual.

Place the main unit in the final

location. This may require bolting on

some of the cover plates before

placement due to obstructions. If

risers are being used, they must be

installed on the unit before final

placement.

Place the secondary booth next to

the main unit. This may require

bolting on some of the cover plates

before placement due to

obstructions. If risers are being

used, they must be installed on the

booth before final placement.

Slide the secondary booth into place

and align the plenum openings and

bolt hole patterns.

Each rectangular opening has a ten

hole bolt pattern. Fasten the

secondary booth to the main unit

using (10) 1/4" - 20 x 1.0" black

socket head cap screw, (20) black

1/4" flat washers, (10) black 1/4"

lock washers, and (10) black 1/4"-20

nuts.

Page 30 of 83

1-866-665-1829

clean-air.com

sales@clean-air.com

Made with FlippingBook - professional solution for displaying marketing and sales documents online