Operations training
High Voltage Standard / V2 PUBLIC HEARING DRAFT 0.1
Module
Session
Instructor to Participant Ratio
Theory
1:12
High Voltage T-Connector Installation
Practical
1:6
Table 9.3.1 - Instructor to Participant Ratio for the High Voltage T-Connector Installation Module
9.4 Equipment Requirements of the High Voltage T-Connector Installation Module
The equipment required for training as listed in Annex 1 must be available and must fulfil national legal requirements as listed in annex 1 where applicable.
When teaching about equipment, a generic approach should be applied whenever possible aiming to avoid only a narrow product specific training. This ensures that participants are ready to adapt to the wide range of equipment they will use in the workplace after completion of this training. However, depending on national or regional legislation, company gap analysis and location specific risk assessments, product specific training or familiarisation may be required, which is the responsibility of the duty holder.
9.5 Timetable of the High Voltage T-Connector Installation Module
The order in which elements of this module are delivered may vary according to the lesson plans prepared for delivering by the training provider.
The delivery of this module must comply with the requirements described in the GWO Requirements for Training .
Lesson
Element
Duration
1. Module introduction
1.1 Safety instructions and emergency procedures 1.2 Facilities 1.3 Introduction
1.4 Aim and objectives 1.5 Ongoing assessment 1.6 Motivation 1.7 Human Factors TOTAL
20 min.
2. HV Cable, Connectors & Components
2.1 HV cable types, applications, specifications 2.2 HV Separable Connectors & components 2.3 Surge Arrestors, other accessories and tools 2.4 Awareness of basic electrical field theory TOTAL
120 min.
Global Wind Organisation / www.globalwindsafety.org
111 / 163
Made with FlippingBook flipbook maker