High Voltage Standard / V2 PUBLIC HEARING DRAFT 0.1
c.
preparation and lubrication
d.
correctly aligning and connecting components
e. applying tools to ensure proper torque on bolted connections
f.
conducting pre-energisation checks
g. illustrate and demonstrate how to evaluate damage
Allocate the participants to work in pairs to follow a work instruction to correctly clean, prepare, lubricate and install a separable T-Connector
Lead participants through a walk-down inspection post cable installation, highlighting cleanup and cable securing and protection measures.
The participants shall:
Practice working in pairs to follow the steps of a work instruction to correctly clean, prepare, lubricate and install a separable T-Connector to a Type-F Bushing
Review their own work and the work of other pairs, sharing peer feedback and discussing compliance with the work instructions and best practices
INSTALLATION SAFE WORKING PRACTICE SESSION
200 min.
The aim of this lesson is to prepare participants to take responsibility to independently apply a work instruction to correctly clean, prepare, lubricate and install separable T-Connectors to a Type-F Bushing using two different connector product types.
After having successfully completed this lesson, the participants can:
27) Take responsibility for safe work practices and effective team coordination during HV connector installation (Ability, intermediate level)
ELEMENT 5.1 - APPLYING WORK INSTRUCTIONS FOR INSPECTION, CLEANING, PREPARATION AND INSTALLATION OF T-CONNECTORS AND SURGE ARRESTORS
Learning objectives: