GCASD Feasibility Study_District Campus 24.02.21

PARKING LOT IMPROVEMENTS (SK – 3A)

The construction of a new parking lot for the building additions needs potentially could utilize the area west of the north synthetic turf field. A tentative layout identifies the addition of 108 parking spaces accessing from the existing parking lot.

Parking Lot Improvement Cost Projections  Excavation / Topsoil Disposal

+/- +/- +/- +/-

$ 10,000 $ 295,000 $ 25,000 $ 25,000

 New Parking Lot / Drainage  Stormwater Management

 Accessories (fencing, lighting, etc)

Total: +/-

$ 355,000

Contingency 15% +/-

$ 53,250

Estimated Total:

+/-

$ 408,250