GCASD Feasibility Study_District Campus 24.02.21

TENTATIVE PROJECT SCHEDULE TURF REPLACEMENT

March 2024

Authorization of Professional Services

March 2024

Construction Documentation Preparation

April 2024

Advertise for Public Bidding

April 2024

Bids Due

May 2024

School Board Review/ Approval of Bids

May 2024

Contracts Prepared / Signed, Contractor Notice to Proceed

May 2024

Submittals

June 2024

Construction Begins

August 15, 2024

Substantial Completion

24