TENTATIVE PROJECT SCHEDULE TURF REPLACEMENT
March 2024
Authorization of Professional Services
March 2024
Construction Documentation Preparation
April 2024
Advertise for Public Bidding
April 2024
Bids Due
May 2024
School Board Review/ Approval of Bids
May 2024
Contracts Prepared / Signed, Contractor Notice to Proceed
May 2024
Submittals
June 2024
Construction Begins
August 15, 2024
Substantial Completion