GCASD Feasibility Study_District Campus 24.02.21

TENTATIVE PROJECT SCHEDULE TURF CONSTRUCTION

March 2024

Authorization of Professional Services

March - May 2024

Municipal / Regulatory Document Preparation

May 2024

Municipal / Regulatory Agency Submissions

May 2024 – January 2025

Municipal / Regulatory Agency Review Process

December 2024 – January 2025 Construction Documentation Preparation

January 2025

Municipal / Regulatory Agency Approvals

January 2025

Advertise for Public Bidding

February 2025

Bids Due

February 2025

School Board Review/ Approval of Bids

February - March 2025

Contracts Prepared / Signed, Contractor Notice to Proceed

April 2025

Submittals

May 2025

Construction Begins

August 15, 2025

Substantial Completion