TENTATIVE PROJECT SCHEDULE TURF CONSTRUCTION
March 2024
Authorization of Professional Services
March - May 2024
Municipal / Regulatory Document Preparation
May 2024
Municipal / Regulatory Agency Submissions
May 2024 – January 2025
Municipal / Regulatory Agency Review Process
December 2024 – January 2025 Construction Documentation Preparation
January 2025
Municipal / Regulatory Agency Approvals
January 2025
Advertise for Public Bidding
February 2025
Bids Due
February 2025
School Board Review/ Approval of Bids
February - March 2025
Contracts Prepared / Signed, Contractor Notice to Proceed
April 2025
Submittals
May 2025
Construction Begins
August 15, 2025
Substantial Completion
25