Palm River Infrastructure Assessment

The following roadways are identified as poor to very poor conditions and are recommended to be considered for major rehabilitation: • H artford Street from railroad to South 54th Street • 54th Street from Causeway Boulevard to St Paul Street • 66th Street south of Madison Avenue • Santa Fe Road west of railroad • Local streets as shown in Figure 11 The following roadways are identified as serious to failed conditions and are recommended to be considered for reconstruction: Pavement Condition and Improvements Continued

Poor to Very Poor

Major Rehabilitation

Serious to Failed

Reconstruction

• Port Sutton Road west of railroad • Trenton Street west of 51st Street • Towaway Avenue from US 41 South to Sagasta Street

Figure 11 also shows the planned, unfunded resurfacing projects within the redevelopment area including Madison Avenue from US 41 to 78th Street, Progress Boulevard from 78th Street to Falkenburg Road, Falkenburg Road from Progress Boulevard to Causeway Boulevard, Santa Fe Road and Port Sutton Road west of US 41, 66th Street, Maydell Drive, and 86th Street. In addition, the FDOT 2022 to 2026 Work Program includes resurfacing on US 41 from Denver Street to 27th Avenue.

25 Section 2

Made with FlippingBook Learn more on our blog