TransGas Comprehensive Tariff
2.2) Customer Specific Facilities All Customer Specific Facilities become System Line after 5 years from the date the facilities were available for use. Any Customer Specific Facilities may become System Line before 5 years if so deemed by TransGas. Customer contribution refunds also apply. If the Customer reimburses TransGas for TransGas Investment, pursuant to the General Business Policies (II. G6.2 Transferring Firm Capacity), the reimbursed amount would be recognized as a Customer contribution amount paid toward the applicable Customer Specific Facility, and would be eligible for capital contribution rebates within the initial 5 years of facility operation. 2.3) Customer Contributions System Lines are not included in the calculation of Customer contributions. 3) Shipper Builds on Behalf of TransGas 3.1) Construction Agreement to Build TransGas and the Customer may enter into a construction agreement to build the pipeline portion of the Customer Specific Facilities at the Customer’s sole cost and risk. The Customer Specific Facilities will remain the property of TransGas. 3.2) TransGas Procedures and Specifications The Customer who builds on behalf of TransGas must do so in accordance with all TransGas’ procedures and specifications. 3.3) Inspection TransGas reserves the right to inspect the construction to ensure that all standards are met. Cost of the inspection is at the Customer’s expense. 3.4) Metering and Tie-in
TransGas will provide and install a meter station at a location of its choice. TransGas will also provide the tie-in to the Gas Transmission System. 3.5) Reimbursement
Once the pipeline portion is completed and a “Certificate of Completion” is issued by TransGas, TransGas will reimburse the Customer an amount equal to the TransGas Investment, not to exceed TransGas' estimated total cost of the project as agreed to prior to construction.
Page 71
Business Practices Overview 1.3 General Business Policies
Made with FlippingBook Ebook Creator