2025-08-29_Ft Worth Safety Action Plan_FINAL_Compressed Com…

Install dynamic speed feedback signage Implement leading pedestrian intervals Install Stop Bar Install Pedestrian Crosswalk (High - Visibility) Consolidate access points Install Pedestrian Refuge Islands Install pedestrian signal heads | Install Pedestrian Pushbutton

Segment

0.95

$30,000.00

Intersection

0.87

$200.00

Intersection

--

$480.00

Intersection

0.90

$25,680.00

Segment

--

$20,160.00

Intersection

0.68

$4,100.00

Intersection

--

$17,360.00

Medium (3 -5 years)

Segment

Install Sidewalks

0.35

$1,424,843.64

Reconfigure Curb Ramps to meet ADA Standard

Intersection

0.65

$248,500.00

Total: $1,774,323.64

Benefit -Cost Analysis The estimated cost - benefit result for Sycamore School Road is 26.56 (Table 14 5). Table 146 summarizes the estimated improvement costs by type and Table 147 summarizes the benefits (dollars) resulting from the implementation of the proposed safety countermeasures.

Table 145 : Sycamore School Road Corridor – Final Cost - Benefit Ratio Benefits Costs

Final Benefit / Cost Ratio

$128,960,000

$4,854,600

26.56

Table 146 : Cost Results for Sycamore School Road Corridor

Annual Maintenance Cost

Service Life

Construction Cost

Improvement Type

Cost (Each)

Quantity

134