Recreation Guide - Winter 2024

Project Highlights • new universal change rooms • new barrier-free washrooms and showers • new ramp entry to pool • new viewing area • new entrance and reception area • new meeting room • new elevator • new accessible parking

Completed to date:

• site prep & hoarding walls erected • demolition • abatement • installation of new water and sanitary lines • completion of foundation walls for the addition

• elevator pit installed • pool ramp prep work

Project Timeline

Spring 2023 • Award of tender • Interior demolition

Summer - Fall 2023 • Exterior construction • Interior construction and finishing

Summer 2024 • All work completed*

*If you’ve ever been involved in a construction project, you know that unexpected challenges often arise. All dates are tentative and subject to change. We appreciate your patience and understanding during this unpredictable time.