AMOUNT OF WORK
From the 1st working day, work must be done in 3 shifts on the production of production equipment for power generation, storage and hydrogen as well as methanol production. The amount of work will already be moved to project space from 7 months.
WORK FUNCTIONS IN THE COMPANY
To manage and distribute the work. This is where many want civil engineers in key positions. I would probably rather have project engineers with a civil engineering education behind them. And when you are up and running in stages, you move from project engineer to special engineer. Since you have all parameters in this project, from canteen care to driving with cryo tanks, you have to be frugal with estimated employees. An estimated guess is at year 3 full operational, 23 full time middle to top management and 83 full time hourly employees.