Ardmac Pharma Solutions : Apr 2022

The walk-on ceiling systemwas designed and installed to facilitate 1.5kN/m ² and 2.5kN/m ² at varying locations complete the Ardmac supply and install Interstitial Area Handrails/Edge Protection and Stair units. The cleanroom floor installations complimented a flush floor finish interface with wall panels, furniture and client equipment. The cleanroom scope spanned c.15,000m ² with Grade C, Grade D and CNC room classifications. As part of design development and field execution a significant amount of trade partner constructability and coordination reviews were held focusing on the build sequencing and timing for planned works. The project was successfully PC’d in May 2021 with a an extremely high quality finish and very satisfied project team and client.

Client:

Wuxi Biologics, Dundalk, Co. Louth

Location: Project Size:

15,000m ²

8