Off-Site Modular Construction : CPD Ardmac
Ardmac Build Off-Site Modular Construction Off-Site Modular Construction
Ardmac Build Off-Site Modular Construction
BioPharma Pressures and Critical Factors for Facility Design BioPharma Market Summary
Business Critical Adaptive facilities that can expand and contract with rapid R&D development or changes in business strategy. Rapid Availability Speed of delivery, allows for clinical stage companies to rapidly progress towards commercialization.
Improved ROI Access to facilities that support current BioPharma R&D and commercialisation ensure improved ROI. Advanced Facility Design Multi-modal and Agile facilities that can meet the technical challenges facing gene and cell therapies.
Ardmac Build Off-Site Modular Construction
Timeline: Off-site versus Traditional Construction Ardmac Build Off-Site Modular Construction
bioGO™ Offsite Build at 10-12 month (Standard Layout)
Design / Engineering Building
Pre- Commissioning at Germfree
Qualification Commissioning Validation
8-10 months Time Savings
Permits and Approval
bioGO™ Build at Germfree
Install
Design Engineering Civil & Site Foundation
Site Construction Concreate Shell Building
Permits and Approval
Traditional Brick and Mortar – Approx. 22 Months
Permits Approval
Site Development Concrete Structural
Building Construction MEP + Fit and Finish
Qualification Commissioning Validation
Design / Engineering
Ardmac Build Off-Site Modular Construction
Timeline: Off-site versus Traditional Construction Ardmac Build Off-Site Modular Construction
bioGO™ Offsite Build at 10-12 month (Standard Layout)
Design / Engineering Building
Pre- Commissioning at Germfree
Qualification Commissioning Validation
8-10 months Time Savings
Permits and Approval
bioGO™ Build at Germfree
Install
Design Engineering Civil & Site Foundation
Site Construction Concreate Shell Building
Permits and Approval
Traditional Brick and Mortar – Approx. 22 Months
Permits Approval
Site Development Concrete Structural
Building Construction MEP + Fit and Finish
Qualification Commissioning Validation
Design / Engineering
Up to 40% Saving on time & Testing Begins at 4 months versus 18 months
Ardmac Build Off-Site Modular Construction