Timeline: Off-site versus Traditional Construction Ardmac Build Off-Site Modular Construction
bioGO™ Offsite Build at 10-12 month (Standard Layout)
Design / Engineering Building
Pre- Commissioning at Germfree
Qualification Commissioning Validation
8-10 months Time Savings
Permits and Approval
bioGO™ Build at Germfree
Install
Design Engineering Civil & Site Foundation
Site Construction Concreate Shell Building
Permits and Approval
Traditional Brick and Mortar – Approx. 22 Months
Permits Approval
Site Development Concrete Structural
Building Construction MEP + Fit and Finish
Qualification Commissioning Validation
Design / Engineering
Ardmac Build Off-Site Modular Construction