Timeline: Off-site versus Traditional Construction Ardmac Build Off-Site Modular Construction

bioGO™ Offsite Build at 10-12 month (Standard Layout)

Design / Engineering Building

Pre- Commissioning at Germfree

Qualification Commissioning Validation

8-10 months Time Savings

Permits and Approval

bioGO™ Build at Germfree

Install

Design Engineering Civil & Site Foundation

Site Construction Concreate Shell Building

Permits and Approval

Traditional Brick and Mortar – Approx. 22 Months

Permits Approval

Site Development Concrete Structural

Building Construction MEP + Fit and Finish

Qualification Commissioning Validation

Design / Engineering

Up to 40% Saving on time & Testing Begins at 4 months versus 18 months

Ardmac Build Off-Site Modular Construction